Sanctuary Construction 2000


Photos of the construction of our sanctuary circa 1999-2000
New Wing Construction




Cement Pour

This page provides information regarding the construction of the new wing of the church which began February 2, 2007. Photo slide shows of the construction are arranged below in chronological order, with the most recent photos nearer the top of the page.  The weekly write-ups contain short blurbs and small photos, which when clicked will lead you to slide shows of the work being done during a particular time period. 

Week 23 Construction
We have a certificate of occupancy.  All items necessary for the issuance of the certificate were completed on Tuesday July 10, 2007 and the first use of the building by any church group was by a group of youngsters from the Vacation Bible School which is going on during the week of July 9-13.  Well done to Harold Morgan, Gene Burnette, Tom Gauntt, Wayne Villadsen, Carl Schuchardt, Robert George and everyone else who continued to work on the punch list in order to get the certificate.  Thanks to Suzan Martin and the Saint Andrew Women for preparing the kitchen for use, and to everyone else who contributed in any way to making this dream come true. 


Final Weekly Report

Week 22 Construction
Week 22 was a week of small but important project completion which moved us very close to a certificate of occupancy, but we did not quite get there as we needed a couple of items completed which we did not accomplish.  Still to be completed are a couple of air conditioning and safety railing tasks and it looks as if those will be completed early next week.  Stay tuned for more info.

Week 21 Construction
Week 21 got us even closer to occupancy with the completion of several important remaining projects.  Carpet is now down in the fellowship hall and has been completed in all other rooms.  Volunteers swept and vacuumed all of the rooms except the fellowship hall which has a plastic protective covering down on much of it.  Work is progressing on the fire protection system, and the two AC units for the fellowship hall are awaiting a part in order to turn them on.  Ceiling tile is in throughout the building.  Landscaping for the remainder of the area surrounding the building is in progress with much of the dirt smoothing being done by volunteers.  The south porch has had the concrete finished and looks very nice.  The cabinets in the bathrooms are being modified to meet ADA standards and will be finished soon.  Quarter-round molding has been placed where needed in much of the building.  All in all it was a good week, and while several items remain to be completed we are getting closer to building use.

Week 20 Construction
Week 20 saw an amazing effort to get the building ready for dedication and it took a concerted effort by our contractors and volunteers to accomplish that.  Windows were cleaned, vinyl work completed, brickwork and porches cleaned, yard prep for sod laid, paving of the parking lots and western drive through paved, sprinkler system repaired and installed, landscaping completed, and tables and chairs for the fellowship hall delivered and stored.  Sunday school rooms and offices were carpeted, tile was laid in the remainder of the hallway and foyers, and the HVAC worked to get three of the five AC units up and running.  All in all it was a great effort and the photos of the weeks activities reflect what was accomplished.

 Week 19 Construction
Brick laying continued, the drive through was prepped, air conditioning duct work progressed nicely, wiring was pulled and finished, the bathrooms were close to completion, and the kitchen had more hardware added.  It will be a race to the finish, but we are hopeful of making the June 17 deadline.  If you have time to volunteer Week 20 will be the week to show up at the building site.

Week 18 Construction
More brick was laid - lots of them, and inside the baseboards and door trim were painted and so were the walls in the offices and Sunday school rooms.  The kitchen was nearer completion with the placement of the marble counter tops and the delivery of sinks and other stainless steel equipment.  Outside, the soffits and trim was being added to and the side walk and entrance pads were poured.  It was a busy week with much progress.  Thanks to all who are making this project move along so well, and especially to David Vosloh, Harold Morgan and the volunteers from the men of St. Andrew By The Sea.  To view some of the events of the week click the small photo below.

Week 17 Construction
Exterior work moved toward completion with more brick being laid.  The north exterior wall was almost completely bricked, and much work had been completed on the last remaining wall, the west wall.  The siding crew began their work on the soffits and porch ceilings which will add a nice finishing touch when completed.  Inside, work continued on the window and door trim, painting of the walls, hanging of the suspended ceiling, electrical work, and heating and air conditioning.  Our volunteers worked on the sprinkler system and electrical wiring for the church sign...both demanding work.  Thanks to David and to them and to all the workmen on the job for bring the building closer to occupancy and use.

Week 16 Construction
Bricks, sheetrock and tile in the kitchen and bathrooms were the big items completed this week.  Cabinets for the kitchen were delivered and stored in the main room of the fellowship hall.  Lots of volunteer effort was needed to keep the site clean and to move old brick left over from the sanctuary construction to the area where the bricklayers were working.  Progress is being made on schedule and perhaps the bricklaying will be nearly completed this week.  David Vosloh and his crews and our volunteers are doing a great job.  Be sure you tell them so when you see them.   Photos of the progress may be viewed by clicking the small photo below.

Week 15 Construction
There was more brick laying and sheetrock hanging this week, and lots of both.  Much of the east side of the building was bricked, and many more rooms inside the structure received sheetrock.

Week 14 Construction
Week 14 was about brick laying and sheetrock and plenty of both.  Take a look at the progress made this week by clicking the small photo below.

Week 13 Construction
Week 13 was the week the shingles went on the roof, electrical work continued, windows were added, and the trench for the power line was dug by hand by volunteers from the congregation.  Photos of all of these may be viewed by clicking the small photo below to initiate the slide show for Week 13.

Week 12 Construction
Progress in week 12 was made in several areas of the construction.  The insulation of the exterior continued in preparation for the brick which will come later, and all of the sheetrock in the ceiling appears to be completed.  Electrical work continued inside as did construction of all of the walls for the classrooms. The sprinkler system and air conditioning duct work continued as well. Volunteers helped with a number of areas and there are still jobs to be done if you have time to commit to a few of the small but important tasks that need to be done as construction goes along.  Contact Harold Morgan or David Vosloh if you would like to help.  A few photos of the progress made during the week can be viewed by clicking the small photo below.

Week 11 Construction
Week 11 saw activity in many areas of construction.  The porches were added to, conduit was laid in the ground for the electrical connections, sheetrock for fire protection above the hanging ceiling was put in place and mudded, additional walls were constructed, outside insulation was attached to the concrete block, and air conditioning duct work was installed in portions of the building.  Volunteers manned shovels, screw drivers and brooms to do their part in seeing to it that construction continued uninterrupted.  Click the small photo below to view some of the activity during week 11.

Week 10 Construction
Week 10 was devoted to truss and roof work, the digging of more trenches for utilities outside the building and work on the interior.  Interior work consisted mainly of the putting up firring strips on which the electrical outlets will be placed and the sheetrock will be nailed. Several more sections of the interior walls were also erected.  Volunteers assisted with the clean-up of the parking lot for Easter Sunday services.  Enjoy the photo in the slide show by clicking the small photo below.

Week 9 Construction
Work continued on the roof and began on the installation of the fire sprinkler system.  Sheet rock was delivered and work on the porches on all four sides of the building saw additional work.  A utility trench was dug on the west and north side of the parking lot and as the week came to a close the roofing crew was still busy custom cutting truss parts and adding plywood decking and the black rubber coating for the plywood.  Volunteers worked at keeping the site clean and filling the utility trench.  It was a busy week with good weather and as Saturday morning came round the roofers were back at their work.  To view photos of the accomplishments of the week click the small photo below for a slide show.

Week 8 Construction
Week eight was about trusses and more trusses and then some, including laying the first decking on the roof.  There was also some more inside construction as well as the pouring of porches on three of the four sides.  To view what took place click the small photo below to start the slide show.

Week 7 Construction
Week seven saw the completion of the laying of the concrete block for the walls and filling them with concrete, the building of  some of the interior rooms in the fellowship hall, the delivery and placement of some of the trusses and the pouring of the foundations for the porches of the new building.  It was a big week and we should all be grateful for the work David Vosloh and the crews he is overseeing for us.  Not only are the paid crews hard at work, so too are the volunteers from the church and the members who are feeding them.  If you want to join in the effort, call Harold Morgan.  To view photos of the events of the week click the three photos below.  The photo on the right contains three photos of work done on Saturday September 18, 2007.

Week 6 Construction
Week six was all about laying block and more block.  It was also the week preparations were made for erecting the load bearing wall inside the building, and materials for that construction were delivered.  To view photos taken during week six click the small photo below.

Week 5 Construction
Week five was the week the slab was poured, smoothed, and began drying.   It was the week that saw the start of framing of the doors and windows by member volunteers of St. Andrew By The Sea and the placement of scaffolding for another 6 courses of brick.  Women of the church brought lunch to the crews of workers and volunteers on Monday, Tuesday and Wednesday.  Thursday was an off day due to weather alerts.  To enjoy the photos of the events of the week, please click the two small photos below.


 

Week 4 Construction
Week four of construction saw progress on on several fronts.  More block was laid, the site was sprayed for termites, leveled and the vapor barrier was put down.  Weather permitting the slab should be poured early next week. Volunteers moved a portion of the playground fence and the slide assembly in order to provide more room for access to the western wall of the new building.  A slide show of some of the activity during the week is available and may be accessed by clicking the small photo below.

Week 3 Construction
Week three of construction was primarily about preparing the foundation for the pouring of the slab, and erecting concrete block walls, placing the rebar in the appropriate places, digging the trenches for water and electricity feeds to the site, and rough in of plumbing and electricity.  There were many volunteers on hand to assist with this work.  If you have a few hours to give, please let Harold Morgan or David Vosloh know when you will be available.

Week 2 Construction
Week two of construction was primarily about pouring the footings and preparing the site for the pouring of the slab next week.  Hired workers and church volunteers were on hand to take care of the many tasks needing to be completed.  Lunch was served by the St. Andrew Women on Monday and Wednesday.  The completion of the footings is a big step toward getting the building completed on time and we were blessed by clear cool weather.  You will notice in the photo the "high tech" truck used to pour the concrete for the footings, as well as the manual labor needed in other places to make the high tech stuff work.  If you look carefully you will see church volunteers moving brick, one at a time, so the road to the north of the sanctuary can be completed.  A slide show of the progress made in week two may be viewed by clicking the small photo below.  Enjoy and remember.......you too can volunteer.

Work Begins
The construction of our new building began Friday February 2, 2007.  The building permit for the foundation was in hand, contractors were on site, volunteers were in place to do their part, and David Vosloh was there to supervise it all.  Realizing that only a few folks could take off from work to be on the site, and aware that the weather was cold and damp, the webmaster took several photos and created a slide show so that all might see the events of the day as they unfolded.  The photos speak for themselves.  You may start the slide show by clicking the small photo below.

HOME UP